Ala. Code § 9-16-84 (1975) Reclamation Plans; Contents

LibraryAlabama Statutes
Edition2023
CurrencyCurrent with legislation from the 2023 Regular and Special Sessions.

(a) Each reclamation plan submitted as part of a permit application pursuant to the provisions of this article shall include, in the degree of detail necessary to demonstrate that reclamation required can be accomplished, a statement of:

(1) The identification of the lands subject to surface coal mining operations over the estimated life of those operations and the size, sequence, and timing of the sub-areas for which it is anticipated that individual permits for mining will be sought;

(2) The condition of the land to be covered by the permit prior to any mining including:

a. The uses existing at the time of the application, and if the land has a history of previous mining, the uses which preceded any mining; and

b. The capability of the land prior to any mining to support a variety of uses giving consideration to soil and foundation characteristics, topography, and vegetative cover, and, if applicable, a soil survey prepared pursuant to Section 9-16-83(b)(15); and

c. The productivity of the land prior to mining, including appropriate classification as prime farm lands, as well as the average yield of food, fiber, forage, or wood products from such lands obtained under high levels of management;

(3) The use which is proposed to be made of the land following reclamation, including a discussion of the utility and capacity of the reclaimed land to support a variety of alternative uses and the relationship of such use to existing land use policies and plans, and the comments of and owner of the surface, state and local governments or agencies thereof which would have to initiate, implement, approve or authorize the proposed use of the land following reclamation;

(4) A detailed description of how the proposed post-mining land use is to be achieved and the necessary support activities which may be needed to achieve the proposed land use;

(5) The engineering techniques proposed to be used in mining and reclamation and a description of the major equipment; a plan for the control of surface water drainage and of water accumulation; a plan, where appropriate, for backfilling, soil stabilization, and compacting, grading, and appropriate revegetation; a plan for soil reconstruction, replacement, and stabilization, pursuant to the performance standards for prime farm lands; an estimate of the cost per acre of the reclamation, including a statement as to how the permittee plans to comply with each of the requirements set out in Section 9-16-90;

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT