RCW 4.24.360 Construction Contract Provision Waiving, Releasing, Etc., Rights of Contractor, Etc., to Damages Or Adjustment For Unreasonable Delay Caused By Contractee, Etc.-Declared Void and Unenforceable-Exceptions

LibraryWashington Statutes
Edition2023
CurrencyCurrent through the 2023 1st Special Session
Year2023
CitationRCW 4.24.360

Any clause in a construction contrac...

This section shall not be construed to void any provision in a construction contract, as defined in RCW 4.24.370, which (1) requires notice of delays, (2) provides for arbitration or other procedure for settlement, or (3) provides for reasonable liquidated damages.