Terms as used in §§ 10-35-1.3 to 10-35-1.6, inclusive, mean:

(1) "Commercial operation date," the first date that a power generation facility is producing electricity on a continuous basis and is delivering electricity to customers;

(2) "Construction date," is the first date earth is excavated for the purpose of constructing the power generation facility;

(3) "Construction period," the time period between the construction date and the commercial operation date;

(4) "Nameplate capacity," the number of kilowatts a power generation facility can produce, as assigned to the power unit by the manufacturer and determined by the secretary;