31 U.S.C. § 3554 Decisions On Protests

LibraryUnited States Statutes
Edition2023
CurrencyCurrent through P.L. 118-34 (published on www.congress.gov on 12/26/2023), except for [P. L. 118-31]
Year2023
Citation31 U.S.C. § 3554

(a)

(1) To the maximum extent practicable, the Comptroller General shall provide for the inexpensive and expeditious resolution of protests under this subchapter. Except as provided under paragraph (2) of this subsection, the Comptroller General shall issue a final decision concerning a protest within 100 days after the date the protest is submitted to the Comptroller General.

(2) The Comptroller General shall, by regulation prescribed pursuant to section 3555 of this title, establish an express option for deciding those protests which the Comptroller General determines suitable for resolution within 65 days after the date the protest is submitted.

(3) An amendment to a protest that adds a new ground of protest, if timely made, should be resolved, to the maximum extent practicable, within the time limit established under paragraph (1) of this subsection for final decision of the initial protest. If an amended protest cannot be resolved within such time limit, the Comptroller General may resolve the amended protest through the express option under paragraph (2) of this subsection.

(4) The Comptroller General may dismiss a protest that the Comptroller General determines is frivolous or which, on its face, does not state a valid basis for protest.

(b)

(1) With respect to a solicitation for a contract, or a proposed award or the award of a contract, protested under this subchapter, the Comptroller General may determine whether the solicitation, proposed award, or award complies with statute and regulation. If the Comptroller General determines that the solicitation, proposed award, or award does not comply with a statute or regulation, the Comptroller General shall recommend that the Federal agency-

(A) refrain from exercising any of its options under the contract;

(B) recompete the contract immediately;

(C) cancel the solicitation issued pursuant to the public-private competition conducted under Office of Management and Budget Circular A-76 or any successor circular;

(D) issue a new solicitation;

(E) terminate the contract;

(F) award a contract consistent with the requirements of such statute and regulation;

(G) implement any combination of recommendations under clauses (A), (B), (C), (D), (E), and (F); or

(H) implement such other recommendations as the Comptroller General determines to be necessary in order to promote compliance with procurement statutes and regulations.

(2) If the head of the procuring activity responsible for a contract makes a finding under section 3553(d)(3)(C)(i)(I) of this title, the Comptroller General shall make recommendations under this subsection without regard to any cost or disruption from terminating, recompeting, or reawarding the contract.

(3) If the Federal agency fails to implement fully the recommendations of the Comptroller General under this subsection with respect to a solicitation for a contract or an award or proposed award of a contract within 60 days after receiving the recommendations, the head of the procuring activity responsible for that contract shall report such failure to the Comptroller General not later than 5 days after the end of such 60-day period.