30 U.S.C. § 1254 Federal Programs

LibraryUnited States Statutes
Edition2023
CurrencyCurrent through P.L. 118-34 (published on www.congress.gov on 12/26/2023), except for [P. L. 118-31]
Year2023
Citation30 U.S.C. § 1254

(a) Promulgation and implementation by Secretary for State

The Secretary shall prepare and, subject to the provisions of this section, promulgate and implement a Federal program for a State no later than thirty-four months after August 3, 1977, if such State-

(1) fails to submit a State program covering surface coal mining and reclamation operations by the end of the eighteen-month period beginning on August 3, 1977;

(2) fails to resubmit an acceptable State program within sixty days of disapproval of a proposed State program: Provided, That the Secretary shall not implement a Federal program prior to the expiration of the initial period allowed for submission of a State program as provided for in clause (1) of this subsection; or

(3) fails to implement, enforce, or maintain its approved State program as provided for in this chapter.

If State compliance with clause (1) of this subsection requires an act of the State legislature, the Secretary may extend the period of submission of a State program up to an additional six months. Promulgation and implementation of a Federal program vests the Secretary with exclusive jurisdiction for the regulation and control of surface coal mining and reclamation operations taking place on lands within any State not in compliance with this chapter. After promulgation and implementation of a Federal program the Secretary shall be the regulatory authority. If a Federal program is implemented for a State, section 1272(a), (c), and (d) of this title shall not apply for a period of one year following the date of such implementation. In promulgating and implementing a Federal program for a particular State the Secretary shall take into consideration the nature of that State's terrain, climate, biological, chemical, and other relevant physical conditions.

(b) Federal enforcement of State program

In the event that a State has a State program for surface coal mining, and is not enforcing any part of such program, the Secretary may provide for the Federal enforcement, under the provisions of section 1271 of this title, of that part of the State program not being enforced by such State.

(c) Notice and hearing

Prior to promulgation and implementation of any proposed Federal program, the Secretary shall give adequate public notice and hold a public hearing in the affected State.

(d) Review of permits

Permits issued pursuant to a previously approved State program shall be valid but reviewable under a Federal program. Immediately following promulgation of a Federal program, the Secretary shall undertake to review such permits to determine that the requirements of this chapter are not violated. If the Secretary determines any permit to have been granted contrary to the requirements of this chapter, he shall so advise the permittee and provide him an opportunity for hearing and a reasonable opportunity for submission of a new application and reasonable time, within a time limit prescribed in regulations promulgated pursuant to section 1251(b) of this title, to conform ongoing surface mining and reclamation operations to the requirements of the Federal program.