43 U.S.C. § 31e Geologic Mapping Program 5-Year Plan

LibraryUnited States Statutes
Edition2023 Edition
CurrencyCurrent through P.L. 118-19 (published on www.congress.gov on 10/06/2023)

(a) In general

The Secretary, acting through the Director, shall, with the advice and review of the advisory committee, prepare a 5-year plan for the geologic mapping program.

(b) Requirements

The 5-year plan shall identify-

(1) overall priorities for the geologic mapping program; and

(2) implementation of the overall management structure and operation of the geologic mapping program, including-

(A) the role of the Survey in the capacity of overall management lead, including the responsibility for developing the national geologic mapping program that meets Federal needs while fostering State needs;

(B) the responsibilities of the State geological surveys, with emphasis on mechanisms that incorporate the needs, missions, capabilities, and requirements of the State geological surveys, into the nationwide geologic mapping program;

(C) mechanisms for identifying short- and long-term priorities for each component of the geologic mapping program, including-

(i) for the Federal component, a priority-setting mechanism that responds to-

(I) Federal mission requirements for geologic map information;

(II) critical scientific problems that require geologic maps for their resolution; and

(III) shared Federal and State needs for geologic maps, in which joint Federal-State geologic mapping projects are in the national interest;