30 U.S.C. § 1005 Lease Term and Work Commitment Requirements

LibraryUnited States Statutes
Edition2023 Edition
CurrencyCurrent through P.L. 118-19 (published on www.congress.gov on 10/06/2023)

(a) In general

(1) Primary term

A geothermal lease shall be for a primary term of 10 years.

(2) Initial extension

The Secretary shall extend the primary term of a geothermal lease for 5 years if, for each year after the 10th year of the lease-

(A) the Secretary determined under subsection (b) that the lessee satisfied the work commitment requirements that applied to the lease for that year; or

(B) the lessee paid in annual payments accordance with subsection (c).

(3) Additional extension

The Secretary shall extend the primary term of a geothermal lease (after an initial extension under paragraph (2)) for an additional 5 years if, for each year of the initial extension under paragraph (2), the Secretary determined under subsection (b) that the lessee satisfied the minimum work requirements that applied to the lease for that year.

(b) Requirement to satisfy annual minimum work requirement

(1) In general

The lessee for a geothermal lease shall, for each year after the 10th year of the lease, satisfy minimum work requirements prescribed by the Secretary that apply to the lease for that year.

(2) Prescription of minimum work requirements

The Secretary shall issue regulations prescribing minimum work requirements for geothermal leases, that-

(A) establish a geothermal potential; and

(B) if a geothermal potential has been established, confirm the existence of producible geothermal resources.

(c) Payments in lieu of minimum work requirements

In lieu of the minimum work requirements set forth in subsection (b)(2), the Secretary shall by regulation establish minimum annual payments which may be made by the lessee for a limited number of years that the Secretary determines will not impair achieving diligent development of the geothermal resource, but in no event shall the number of years exceed the duration of the extension period provided in subsection (a).

(d) Transition rules for leases issued prior to August 8, 2005

The Secretary shall by regulation establish transition rules for leases issued before August 8, 2005, including terms under which a lease that is near the end of its term on August 8, 2005, may be extended for up to 2 years-

(1) to allow achievement of production under the lease; or

(2) to allow the lease to be included in a producing unit.

(e) Geothermal lease overlying mining claim

(1) Exemption

The lessee for a geothermal lease of an area overlying an area subject to a mining claim for which a plan of operations has been approved by the relevant Federal land management agency is exempt from annual work requirements established under this chapter, if development of the geothermal resource subject to the lease would interfere with the mining operations under such claim.

(2) Termination of exemption

An exemption under this paragraph expires upon the termination of the mining operations.

(f) Termination of application of requirements

Minimum work requirements prescribed under this section shall not apply to a geothermal lease after the date on which the geothermal resource is utilized under the lease in commercial quantities.