30 U.S.C. § 1258 Reclamation Plan Requirements

LibraryUnited States Statutes
Edition2023
CurrencyCurrent through P.L. 118-34 (published on www.congress.gov on 12/26/2023), except for [P. L. 118-31]
Year2023
Citation30 U.S.C. § 1258

(a) Each reclamation plan submitted as part of a permit application pursuant to any approved State program or a Federal program under the provisions of this chapter shall include, in the degree of detail necessary to demonstrate that reclamation required by the State or Federal program can be accomplished, a statement of:

(1) the identification of the lands subject to surface coal mining operations over the estimated life of those operations and the size, sequence, and timing of the subareas for which it is anticipated that individual permits for mining will be sought;

(2) the condition of the land to be covered by the permit prior to any mining including:

(A) the uses existing at the time of the application, and if the land has a history of previous mining, the uses which preceded any mining; and

(B) the capability of the land prior to any mining to support a variety of uses giving consideration to soil and foundation characteristics, topography, and vegetative cover, and, if applicable, a soil survey prepared pursuant to section 1257(b)(16) of this title; and

(C) the productivity of the land prior to mining, including appropriate classification as prime farm lands, as well as the average yield of food, fiber, forage, or wood products from such lands obtained under high levels of management;

(3) the use which is proposed to be made of the land following reclamation, including a discussion of the utility and capacity of the reclaimed land to support a variety of alternative uses and the relationship of such use to existing land use policies and plans, and the comments of any owner of the surface, State and local governments or agencies thereof which would have to initiate, implement, approve or authorize the proposed use of the land following reclamation;

(4) a detailed description of how the proposed postmining land use is to be achieved and the necessary support activities which may be needed to achieve the proposed land use;

(5) the engineering techniques proposed to be used in mining and reclamation and a description of the major equipment; a plan for the control of surface water drainage and of water accumulation; a plan, where appropriate, for backfilling, soil stabilization, and compacting, grading, and appropriate revegetation; a plan for soil reconstruction, replacement, and stabilization, pursuant to the performance standards in section 1265(b)(7)(A), (B), (C), and (D) of this title, for those food, forage, and forest lands identified in section 1265(b)(7) of this title; an estimate of the cost per acre of the reclamation, including a statement as to how the permittee plans to comply with each of the requirements set out in section 1265 of this title;

To continue reading