31 U.S.C. § 3553 - Review of protests; effect on contracts pending decision

Cite as31 U.S.C. § 3553

(a) Under procedures prescribed under section 3555 of this title, the Comptroller General shall decide a protest submitted to the Comptroller General by an interested party.

(b)

(1) Within one day after the receipt of a protest, the Comptroller General shall notify the Federal agency involved of the protest.

(2) Except as provided in paragraph (3) of this subsection, a Federal agency receiving a notice of a protested procurement under paragraph (1) of this subsection shall submit to the Comptroller General a complete report (including all relevant documents) on the protested procurement-

(A) within 30 days after the date of the agency's receipt of that notice;

(B) if the Comptroller General, upon a showing by the Federal agency, determines (and states the reasons in writing) that the specific circumstances of the protest require a longer period, within the longer period determined by the Comptroller General; or

(C) in a case determined by the Comptroller General to be suitable for the express option under section 3554(a)(2) of this title, within 20 days after the date of the Federal agency's receipt of that determination.

(3) A Federal agency need not submit a report to the Comptroller General pursuant to paragraph (2) of this subsection if the agency is sooner notified by the Comptroller General that the protest concerned has been dismissed under section 3554(a)(4) of this title.

(c)

(1) Except as provided in paragraph (2) of this subsection, a contract may not be awarded in any procurement after the Federal agency has received notice of a protest with respect to such procurement from the Comptroller General and while the protest is pending.

(2) The head of the procuring activity responsible for award of a contract may authorize the award of the contract (notwithstanding a protest of which the Federal agency has notice under this section)-

(A) upon a written finding that urgent and compelling circumstances which significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General under this subchapter; and

(B) after the Comptroller General is advised of that finding.

(3) A finding may not be made under paragraph (2)(A) of this subsection unless the award of the contract is otherwise likely to occur within 30 days after the making of such finding.

(d)

(1) A contractor awarded a Federal agency contract may, during the period described in paragraph (4), begin performance of the contract and engage in any related activities that result in obligations being incurred by the United States under the contract unless the contracting officer responsible for the award of the contract withholds authorization to proceed with performance of the contract.

To continue reading