33 U.S.C. § 2231 Study of Water Resources Development Projects By Non-Federal Interests

LibraryUnited States Statutes
Edition2023
CurrencyCurrent through P.L. 118-34 (published on www.congress.gov on 12/26/2023), except for [P. L. 118-31]
Year2023
Citation33 U.S.C. § 2231

(a) Submission to Secretary

(1) In general

A non-Federal interest may undertake a federally authorized feasibility study of a proposed water resources development project, or, upon the written approval of the Secretary that the modifications are consistent with the authorized purposes of the project, undertake a feasibility study on modifications to a water resources development project constructed by the Corps of Engineers, and submit the study to the Secretary.

(2) Guidelines

To assist non-Federal interests, the Secretary, as soon as practicable, shall issue guidelines for the formulation of feasibility studies of water resources development projects undertaken by non-Federal interests to-

(A) ensure that any feasibility study with respect to which the Secretary submits an assessment to Congress under subsection (c) complies with all of the requirements that would apply to a feasibility study undertaken by the Secretary; and

(B) provide sufficient information for the formulation of the studies, including processes and procedures related to reviews and assistance under subsection (e).

(b) Review by Secretary

(1) In general

The Secretary shall review each feasibility study received under subsection (a)(1) for the purpose of determining whether or not the study, and the process under which the study was developed, each comply with Federal laws and regulations applicable to feasibility studies of water resources development projects.

(2) Timing

The Secretary may not submit to Congress an assessment of a feasibility study under this section until such time as the Secretary-

(A) determines that the feasibility study complies with all of the requirements that would apply to a feasibility study undertaken by the Secretary; and

(B) completes all of the Federal analyses, reviews, and compliance processes under the National Environmental Policy Act of 1969 ( 42 U.S.C. 4321 et seq.), that would be required with respect to the proposed project if the Secretary had undertaken the feasibility study.

(3) Initiation of review

(A) Request

(i) Submission

The non-Federal interest may submit to the Secretary a request that the Secretary initiate the analyses, reviews, and compliance processes described in paragraph (2)(B) with respect to the proposed project prior to the non-Federal interest's submission of a feasibility study under subsection (a)(1).

(ii) Effect

Receipt by the Secretary of a request submitted under clause (i) shall be considered the receipt of a proposal or application that will lead to a major Federal action that is subject to the requirements of section 102(2)(C) of the National Environmental Policy Act of 1969 ( 42 U.S.C. 4332(2)(C) ) that would be required if the Secretary were to undertake the feasibility study.

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT