25 U.S.C. § 3506 Wind and Hydropower Feasibility Study

LibraryUnited States Statutes
Edition2023
CurrencyCurrent through P.L. 118-34 (published on www.congress.gov on 12/26/2023), except for [P. L. 118-31]
Year2023
Citation25 U.S.C. § 3506

(a) Study

The Secretary of Energy, in coordination with the Secretary of the Army and the Secretary, shall conduct a study of the cost and feasibility of developing a demonstration project that uses wind energy generated by Indian tribes and hydropower generated by the Army Corps of Engineers on the Missouri River to supply firming power to the Western Area Power Administration.

(b) Scope of study

The study shall-

(1) determine the economic and engineering feasibility of blending wind energy and hydropower generated from the Missouri River dams operated by the Army Corps of Engineers, including an assessment of the costs and benefits of blending wind energy and hydropower compared to current sources used for firming power to the Western Area Power Administration;

(2) review historical and projected requirements for, patterns of availability and use of, and reasons for historical patterns concerning the availability of firming power;

(3) assess the wind energy resource potential on tribal land and projected cost savings through a blend of wind and hydropower over a 30-year period;

(4) determine seasonal capacity needs and associated transmission upgrades for integration of tribal wind generation and identify costs associated with these activities;

(5) include an independent tribal engineer and a Western Area Power Administration customer representative as study team members; and

(6) incorporate, to the extent appropriate, the results of the Dakotas Wind Transmission study prepared by the Western Area Power Administration.

(c) Report

Not later than 1 year after August 8, 2005, the Secretary of Energy, the Secretary, and the Secretary of the Army shall submit to Congress a report that describes the results of the study, including-

(1) an analysis and comparison of the potential energy cost or benefits to the customers of the Western Area Power Administration through the use of combined wind and hydropower;

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT